← Back to SOPs catalog
Keedian operations · Standard procedure
Backup autonomy below minimum.
Estimated ride-through — the UPS battery bridge plus the generator's run-time on available fuel — falls below the building's agreed minimum at the present load. If the grid fails now, backup does not cover the outage to restoration. Read-only: Keedian surfaces the shortfall and the leg responsible and refers it to the customer and the electrical / power vendor.
01 Detail
Trigger, action plan, and escalation criteria.
optimization_metric
continuity
high
managed tier
AI: hybrid
- Related metric
backup_autonomy
- Trigger
estimated_autonomy < agreed_minimum_autonomy (at present load)
- Value drivers
-
Operational continuity
- Preconditions
- The minimum required autonomy agreed per building; the UPS battery-autonomy and generator fuel-level signals mapped and verified; the critical-load basis recorded so the estimate is computed against the loads that matter.
- Human role
- AI recomputes the estimate at load, attributes the shortfall to the leg responsible (UPS battery vs generator fuel), and routes the referral; operators confirm the estimate against the agreed minimum, notify the customer, and coordinate the vendor.
- Action plan
-
(1) Confirm the estimate is reported against the building's agreed minimum, not a default, and that it is sustained rather than a single interval during a load peak.
(2) Attribute the shortfall to the leg responsible — a UPS bank short on the bridge, or the generator leg short on fuel — so the referral is the right one (battery service vs refuelling).
(3) Treat the number as a live estimate, not a guarantee — it moves with load and asset health; re-check at the present load before escalating.
(4) Keedian surfaces which leg is short and by how much and hands it to the customer and the electrical / power vendor; refuelling, battery replacement, and load management stay with them.
- Escalation
-
(1) Estimated autonomy below the agreed minimum while the primary source is already stressed or flapping → direct customer + vendor alert; the shortfall is about to be tested.
(2) A below-minimum estimate on a load the customer has flagged as material → out-of-cycle notification.
(3) Buildings trending toward the minimum month over month → carry into the MBR as a battery-replacement or fuel-management program candidate (magnitude expected — pending validation; offices have no named Keedian reference deployment).
- Prevention
-
(1) Agree the minimum required autonomy per building at onboarding as the reference the estimate is reported against.
(2) Verify the battery-autonomy and fuel-level signals map correctly so the estimate reflects the building, not a default curve.
(3) Recompute the estimate as load changes and trend both legs so a slow erosion is visible before it crosses the minimum.