← Back to SOPs catalog
Keedian operations · Standard procedure
Lamp life threshold approaching.
Cumulative burn hours on a circuit approach the lamps' rated life — failures will start to cluster, and the burn-hour record is the evidence for an efficiency rebate.
01 Detail
Trigger, action plan, and escalation criteria.
optimization_metric
lighting
low
essential tier
AI: hybrid
- Related metric
burn_hours
- Trigger
cumulative_burn_hours approaching lamp_rated_life
- Value drivers
-
Asset lifespan
Avoided truck rolls
- Preconditions
- Per-circuit on/off state accumulated over time; lamp type + rated life on file.
- Human role
- Plans the proactive group relamp and assembles the rebate evidence.
- Action plan
-
(1) Confirm cumulative burn hours are approaching the lamps' rated life for the circuit.
(2) Plan a proactive group relamp before failures cluster — one scheduled visit instead of repeat emergency lamp-out calls.
(3) Where an LED-retrofit rebate is conditional on minimum burn hours, export the cumulative burn-hour record as proof of the condition.
- Escalation
-
(1) Burn hours far above the space band with no operational reason -> a stuck-on circuit or a schedule gap (cross-check Schedule Compliance) is wasting both energy and lamp life.
- Prevention
-
(1) Track cumulative burn hours per circuit against rated life so relamps are planned, not reactive.