Whether the rack's pump-down sequence completes as commissioned — reaching its pump-down setpoint within its delay, not aborting, and not repeating abnormally. A pump-down that fails to reach setpoint, is left incomplete, or short-cycles risks liquid return and compressor damage. Setpoint and delay alone do not activate the metric: it requires a pump-down request / state plus suction pressure and timestamps as evidence the sequence actually ran.

04 Alarms

Principal alarms derived from this metric

The table below summarizes the alarms that fire directly from Rack Pump-Down Performance. Each row links to the full operational detail (trigger, preconditions, action plan, human role, escalation, prevention) in the SOPs catalog.

AlarmDescriptionSeverityTierAI executes?Value driversSOP
Pump-down does not reach setpoint A pump-down request fails to reach its configured Pump Down Setpt within Pump Down Delay. An incomplete pump-down leaves refrigerant where it should not be and risks liquid return and compressor damage on the next start. High Managed Hybrid Asset lifespan · Operational continuity · Energy savings Open SOP →
Pump-down aborted or incomplete A pump-down sequence is aborted or left incomplete before it finishes. As with a pump-down that never reaches setpoint, an aborted sequence risks liquid return and compressor damage and points to a controls or valve fault. High Managed Hybrid Asset lifespan · Operational continuity · Energy savings Open SOP →
Pump-down repeats abnormally The pump-down sequence repeats more often than the commissioned observation window expects — a short-cycling pattern that stresses compressors and points to a leak-back, valve, or control fault rather than a single failed sequence. High Managed Hybrid Asset lifespan · Operational continuity · Energy savings Open SOP →
05 Actions

What to do based on the alarm

The action plan for each alarm lives on its own SOP page in the SOPs catalog — with the diagnostic steps, human role, value drivers, escalation, and prevention specific to that alarm. The list below maps each alarm to its SOP.

  • Pump-down does not reach setpoint → — A pump-down request fails to reach its configured Pump Down Setpt within Pump Down Delay. An incomplete pump-down leaves refrigerant where it should not be and risks liquid return and compressor damage on the next start.
  • Pump-down aborted or incomplete → — A pump-down sequence is aborted or left incomplete before it finishes. As with a pump-down that never reaches setpoint, an aborted sequence risks liquid return and compressor damage and points to a controls or valve fault.
  • Pump-down repeats abnormally → — The pump-down sequence repeats more often than the commissioned observation window expects — a short-cycling pattern that stresses compressors and points to a leak-back, valve, or control fault rather than a single failed sequence.